SL. No. | Project Name | Client | Contract Amount
(incl. Currency) |
Period(YY/MM) | |
Start | Finish | ||||
1 | Supervision of New Dormitory and Guest House | A &A Textiles | USD 3,15,567.00 | 06.08.2021 | Ongoing |
2 | Supervision of Connection road to Factory at Kaliganj | Multazim Spinning Mills Ltd | USD 2,15,785.00 | 23.03.2021 | Ongoing |
3 | Supply and Installation of Double lane Steel truss for Highway Bridges with Concrete deck for 1 (one) span of 107.25 meter (in between P8 & P11) for the Incomplete Bridge over the Lohalia River at Sadar Upazila under Patuakhali District during the year 2018-2019 | LGED, Patuakhali | 21,17,84,106.00 | 2019
June |
On-Going |
4 | Construction Supervision of factory Building and Warehouse | A Puls Sweater Ltd. | 79,836,000.00 | 12.3.2020 | 12.9.2021 |
5 | Interior design & Building Construction supervision | Triangles GROUP | 98,489,464.00 | 010.5.2019 | 17.09.2021 |
6 | Guest House Design & Construction Supervision Projects | Afrin Spinning Mills Ltd. | 75,894,500.00 | 16.02.2020 | 01.11.2021 |
7 | Connecting Road & Boundary wall Construction Supervision | SSR GROUP | 89,982,600.00 | 10.05.2021 | 24.11.2021 |
8 | Construction of Supervision of administrative building Construction work | ANWAR LANDMARK | 88,764,,500.00 | 05.04.2020 | 03.01.2021 |
9 | Construction of Supervision of works Dormitory building project at BSCIC | M/S ANIK CONSTRUCTION | 87,454,587.00 | 15.05.2019 | 12.11.2020 |
10 | Rest House and dormitory building design & construction supervision | Pubali Construction Company Limited | 75,454,578 | 20.09.2019 | 09.07.2020 |
11 | Supervision of Factory building Interior Work (including thai, aluminium, glass door, ceiling). | Nahid Group | 4,78,654.00 | 2017
January |
2017
June |
12 | Designing and supervision of building construction work. | Nahid Group | 3,98,156.00 | 2018
February |
2018
September |
13 | Designing of Factory building Construction work. | Century Spinning Mills Ltd. | 5,88,548.00 | 2016
August |
2017
July |
14 | Supervising construction works of factory building (knit
Factory) project at tongi, gazipur. |
ACE APPAREL LTD | 5,75,100.00 | 2020
January |
2020
November |
15 | Connecting Road Construction Supervision of Mesh Garments (pvt) Unit-1 Ltd. | Unibond Engineering & Technologies | 4,87,800.00 | 2018
February |
2018
October |
16 | Administrative building extension work design & supervision at tongi, gazipur, dhaka | Renasa Trade International | 4, 68, 540.00 | 2020
December |
2021
June |
17 | Supervision of Factory building extension work. | Knit Concern Group | 2,45,445.00 | 2019
March |
2019
November |
18 | Painting and Redesigning of Factory Building | Viyellatex | 3,20,166.00 | 2019
July |
2020
February |
19 | Mechanical Designing Factory building work | Monno Fabrics Ltd. | 5,80,500.00 | 2021
January |
2021
October |
20 | Factory building construction supervision | Afrin Spinning Mills Ltd. | 4,98,870.00 | 2017
December |
2018
November |
21 | Construction Supervision of Boundary Wall | Bigapple Builders Ltd. | 4,36,000.00 | 2018
September |
2019
June |
22 | Electrical Work for Factory building | Stylecraft Limited | 4,80,900.00 | 2018
February |
2018
November |
23 | 4 Nos. Steel Mooring Buoy
Dia: 5500mm, Height: 2360mm |
BM Energy(BD) Ltd, 1206/A Nasiraba, Bayzid Thana Road, Chottagram. | 2,95,00,000.00 | 2016
July |
2018
March |
24 | Different steel Works for Gumti Bridge | OSJI Joint Venture | 10,00,000,00.00 | 2016
February |
2018
October |
25 | Supply & installation of 101.035 meter Double lane steel truss for highway bridge with provision of concrete deck for one span of for the under construction Sheikh Lutfor Rahman Bridge ( Patgati Bridge) | Roads & Highways Department | 16,98,49,412.19 | 2012
April |
2013
June |
26 | Supply & Supervision during carriage & installation of double lane steel truss for highway with provision of concrete deck for 1 (One) span of 115.00 meter under construction surma bridge over the River Surma at Sunamgonj | Roads & Highways Department | 12,63,48,920.00 | 2013
March |
2014
May |
27 | Construction & Supply of shore pipe with flanges at both sides (Length of each pipe: 20 ft) with nut-bolts and rubber gasket; (a) 20 inch pipe—–350 pcs, (2) 18 inch pipe—– 1530 pcs | VOSTA LMG Karnafuly Joint Venture Consortium Ltd.
Strand road, Majhirghat, Chittagong-4000 |
80,00,000.00 | 2013 | 2013 |
27 | Preparation of design & new construction of series of coastal bulk carrier of 2200 DWT capacity;
(1) MV River Dream-1,(2) MV River Dream-2, (3) MV River Dream-3, (4) MV River Dream-4 |
River Dream Navigation Ltd. Land View, 8th Floor, Gulshan, Dhala-1212 | 19,50,000.00 | 2012 | 2013 |
28 | Design, Supply, Installation, Testing and Commission of Structure for Fuel unloading Station at Daudkandi 50 MW Power Plant | CCC Engineering Ltd.
H-485, R-8, DOHS Baridhara, Dhaka-1206 |
62,00,000.00 | 2011 | 2012 |
29 | Design, Supply, Installation, Testing and Commission of Structure for Fuel unloading Station at Baghabari 50 MW Power Plant on Trunkey Basis. | 70,00,000.00 | 2011 | 2012 | |
30 | Supply of 708 meter Single Lane Portable Steel Bridge of Different Spans | Roads & Highways Department | 14,90,29,035.32 | 2014
March |
2015
Mar |
31 | Supply of 475 meter Single Lane Portable Steel Bridge of Different Spans | Roads & Highways Department | 21,38,01,631.00 | 2017 May | 2018 |
32 | Supply and Supervision during Carriage & Installation of Double lane Steel truss for Highway Bridges with provision of concrete deck for 1 (one) span of 115.00 meter (in between P3 & P4) for the under construction Bridge over the River Surma at Chhatak, Sunamgonj under Sunamgonj road division of Sylhet Road Circle, Sylhrt during the year 2018-2019 (GD-1). | Roads & Highways Department | 15,73,61,575.00 | 2018
December |
2021 |
33 | Procurement of 573 meter Single Lane Portable Steel Bridge of Different Spans for the Roads and Highways Department | Roads & Highways Department | 29,54,54,792 | 2020
January |
2021 |